Site Selection Committee Meeting — May 27, 2026

Lebanon WWTP Site Selection — Public Record Archive  |  Return to main page

Video recording (YouTube)  —  Meeting began 4:00 p.m., City of Lebanon Administration Building

Committee Introduction and Purpose

This was the first public meeting of the Site Selection Committee. Chair Jeff Baines opened by reading from the authorizing resolution: the committee's purpose is to independently review, evaluate, and rank all viable sites for the new wastewater treatment plant. The committee is advisory only — it has no authority to spend money, acquire property, or negotiate with anyone. Final decisions rest with city council. The goal is to identify at least three viable sites, ranked in order of preference, and return a preliminary report to council within 45 days and a final recommendation within 90 days.

Committee members present: Jeff Baines (chair), Jody Vance, Caleb Thorne, Regina Santana, Tom Clemmons, Phil Morehead, Joey Carmack; Steve Jones (engineer/consultant, non-voting). Dave Dixon and Randy Lane had not yet attended. A vice chair and secretary were also identified. (An earlier version of this line listed “Jeff Bangs” and “Bill Bines” as separate attendees — both were transcription garbles of Jeff Baines.)

Scoring Matrix Adopted

Jody Vance presented a preliminary five-criterion scoring matrix for committee adoption. The criteria (in alphabetical order, not priority order):

Each criterion carries an importance factor of 1–3 (set once by each committee member, applied uniformly to all sites), and each site is scored 1–5 per criterion. The weighted score is the product of the two. The matrix was described as a preliminary shortlisting tool; a more detailed second-stage matrix would be developed for the final candidates.

The committee adopted the matrix by motion and vote before beginning site review, specifically to establish criteria before examining individual sites.

Engineer Site Presentations

Steve Jones (engineer/consultant) reviewed each of the 15 candidate sites, providing acreage, percentage of flood plain, and estimated force main connection distance (at approximately $1,000/linear foot for a 36-inch pipe; two pipes are needed to close the loop, so off-force-main distance drives cost at roughly $4,000/ft of property offset).

A minimum of 60 buildable acres (excluding flood plain) was established as the threshold for a viable site — enough for the initial facility, a future expansion phase, and a 100-foot buffer on all sides. Current plant capacity is 10 MGD; the new facility is designed for 20 MGD Phase 1, expandable to 40–50 MGD.

SiteAcresFlood PlainForce Main DistanceNotes
12353.2%~3,600 ftLarge track; single home and outbuildings; topographical variation
2669.6%<100 ftCombined force main adjacent to property; right at 60-acre minimum; some residential homes nearby
3702%~800 ftHillside terrain; significant grading required; no structures
4491.9%<100 ftUnder 60 acres; adjacent to Site 3 (combined ~100 acres); Coles Ferry Pike frontage; no structures
51870%~250 ftBoth force mains adjacent; existing structures; no flood plain
62234.8%~3,300 ftLarge; requires two force main connections (farthest side of both mains)
79718.5%Longest of all sitesFarthest site reviewed; high flood plain; existing structure
816441%~4,250 ftOne force main on site; high flood plain; off Trice Road area
9105~71%~2,800 ftMostly flood plain/floodway; existing structures; Coles Ferry Pike frontage
1093~6,500 ftAcross from Site 9; force main distance greater due to measurement across Site 9 span
11560%~6,500 ftAdjacent to Site 10; smaller; no flood plain
123568.9%~4,000 ftLarge track
135999.8%AdjacentAlmost entirely flood plain/floodway; gas easement through property; good road frontage; adjacent to both force mains
14240%AdjacentDirectly across from existing plant; under 60 acres; existing business (Permapipe); expansion would require split-plant operation with existing facility
154746.4%~3,500 ftUnder 60 usable acres; split-plant operation required; existing uses on site

The engineer noted that Sites 14 and 15 would require treatment to occur in two locations — some at the existing plant and some at the new site — given their proximity to and size relative to the current facility.

Additional Sites Discussed

Several committee members and members of the public suggested sites beyond the original 15:

The resolution allows the committee to consider sites beyond those initially identified. New sites were to be sent to the engineer by the following week to allow time for preparation before the next meeting.

Key Technical Discussion

Public Comment Highlights

The meeting room was at or near capacity; overflow attendees were outside the building. Applause followed most public speakers. The committee emphasized throughout that only tax parcel numbers — not owner names — would be used in the formal evaluation process.

Next Steps

These notes were prepared by Todd Roark from the YouTube auto-generated transcript of the May 27, 2026 meeting and represent a summary, not a verbatim record. The official minutes, once approved by the committee, are the authoritative record.